经营单元:
伊拉克安巴尔项目
分包招标项目:
Soil Geotechnical Investigation And Survey Work for gas pipeline伊拉克安巴尔管线项目管线地形测量和勘探标段
投标截止日期/开标日期(**时间):
2026-12-14 15:00:00
报名截止日期(**时间):
2026-12-09 17:00:00
联系人:
Jiao Changjia
联系电话:
+964 ****689558
计划开工日期:
2026-12-25
计划竣工日期:
2027-02-23
招标机构:
Inviting Public Bidding Management Office, SEPCOIII Electric Power Construction Corporation
招标机构地址:
Yijie Hongtai Building, Tong'an Road 882-1, Laoshan District, Qingdao City, Shandong Province
招标机构联系人:
Chu Yue
招标机构联系电话:
0532-****7064
项目业主:
the Iraqi Ministry of Electricity (MOE) and the Iraqi Ministry of Petroleum (MOO)
项目概况及招标范围:
1.Project Location: The project is located in northwestern Anbar province, Iraq, from the Akkas Gas Field to the Anbar Combined Cycle Power Plant. 2.Project Scale: This natural gas pipeline has a maximum transmission capacity of 480 mm SCFD and includes the AKKAS gas field pipeline control room, K3 transfer station, Anbar pressure relief station, and 11 LBV valve stations, with a length of approximately 250 km. 3.Soil geotechnical investigation and survey work for pipeline Including but not limited to the following work: Topographic Survey, Geological Investigation, Laboratory Test,the approval of the soil investigation by Owner,etc.The detailed scope and interface will be shown on the drawing with coordinate attached; all works included but not limited that described in“the scope of work”,“BOQ”and “technical specification”within the interface boundary line
投标人资格要求:
1.Bidder's Qualification and Competence Requirements: The bidders must have an independent legal entity registered within the Iraq and provide a valid business license, and possess relevant construction experience. 2.Performance requirements: The bidder must have at least 1 similar contract performance record . The bidder is required to provide a scanned copy of the contract that can prove the requirements of this bidding.
其他要求:
投标保证金:
3,000
投标保证金币种:
美元